Tag Archives: guidance

PRINCE2 Foundation Certification Exam

ProjectingIT, APMG ATO, presents PRINCE2 foundation certification exam guidance. PRINCE2 Foundation exam styles questions and how to pass it in your 1st try.


  1. PRINCE2 Qualifications Guidance for PRINCE2 Foundation Exam
  2. About projectingIT Leading APMG ATO 5,000 + certified project managers 4.75 / 5.0 avg. feedback rating Best pass rate in the industry Blended courses > Live!, Online & Classroom Pass Guarantee or we pay your re-exam fees Presented by Ashish Dhoke, PRINCE2 trainer @ projectingIT, a PRINCE2 ATO projectingIT www.projectingIT.com PRINCE2® is a registered trade mark of the Cabinet Office
  3. Objective of the Foundation Exam The candidate should demonstrate the understanding of PRINCE2 principles, themes, processes, techniques and roles
  4. What you should know for the Foundation Exam -> The 7 principles and how they are supported -> The purpose of each theme and how the 7 themes are used -> The purpose, objectives, activities of the 7 processes -> The PRINCE2 team structure, roles and their responsibilities -> The purpose of each management product e.g. Business Case
  5. Structure of the Paper Multiple choice 1 hour exam, closed book exam 75 questions 5 trial questions not counted in scores 35/70 to pass the exam (50%) closed book, objective style each question has ONLY one right answer
  6. Foundation Exam dation exam is assing the Foun NOTE: p r the PRINCE2 uired to appear fo req ctitioner Exam Pra
  7. Foundation Exam your Answers Marking A B C D
  8. Test style => Standard Which individual role is ultimately accountable for the project? a) Executive b) Project Manager c) Senior Supplier d) Senior User
  9. Test style => Standard Which individual role is ultimately accountable for the project? a) Executive ✔ b) Project Manager c) Senior Supplier d) Senior User
  10. Test style => Negative Which is NOT one of the process in PRINCE2? a) Starting up a Project b) Directing a Project c) Closing a Project d) Change Control
  11. Test style => Negative Which is NOT one of the process in PRINCE2? a) Starting up a Project b) Directing a Project c) Closing a Project d) Change Control ✔
  12. Test style => List Which other roles the Project Manager can also perform? 1) Project Support 2) Change Authority 3) Senior Supplier 4) Team Manager a) 1, 2, 3 b) 1, 3, 4 c) 1, 2, 4 d) 2, 3, 4
  13. Test style => List Which other roles the Project Manager can also perform? 1) Project Support 2) Change Authority 3) Senior Supplier 4) Team Manager a) 1, 2, 3 b) 1, 3, 4 c) 1, 2, 4 ✔ d) 2, 3, 4
  14. Test style => Missing Word The reasons for undertaking the project must drive the [ ? ] and should be used to continually align the project progress to the business objective. a) delivery strategy b) decision making c) benefits management strategy d) tolerance approach
  15. Test style => Missing Word The reasons for undertaking the project must drive the [ ? ] and should be used to continually align the project progress to the business objective. a) delivery strategy b) decision making ✔ c) benefits management strategy d) tolerance approach
  16. want to TRY some more? note down your answers then.
  17. Question #1 What distinguishes a project from regular business operations? a) Projects offer benefits b) Introduces business change c) Manages stakeholders d) Incurs cost
  18. Question #2 Which is one of the six aspects of project performance that needs to be managed? a) Customers b) People c) Benefits d) Processes
  19. Question #3 Which is the characteristic of a project? a) Low risk b) Avoids stress and strains between organizations c) Business as usual d) Cross-functional
  20. Question #4 Which of the following is NOT a PRINCE2 principle? a) Learn from Experience b) Manage by Exception c) Focus on Products d) Deliver on Time
  21. Question #5 Which other role the Project Manager can also play? a) Project Assurance b) Team Manager c) Executive d) Senior User
  22. Answers! 1 => B 2 => C 3 => D 4 => D 5 => B