Calender

Microsoft Project Fundamentals 2007

Jul Mumbai - 2days
Jul Pune - 2 days
Aug Mumbai - 2 days

PMP Preparation Program - PMBOK edition 4

Jul Mumbai - 4 days
Aug Delhi - 4 days
Aug Mumbai - 2 days

PRINCE2 - Announcing Shortly

Aug Mumbai - 3 days
Aug Delhi - 3 days
Aug Pune - 3 days

Project Management

Mumbai - 4 days
Sep Pune - 4 days

Testimonials

PMP Workshop - Chennai

Fun and Energetic Project Manager with lot of hands on experience which he overlaid extremely well on the PMP course to help me understand the PM concepts and of course, crack the exam.

Hemanth Panyam,
AthenaHealth India (NYSE:ATHN)

more

Ask the Expert

Send your Microsoft Project related queries or issues to our expert. Ashish may be able to help you in troubleshooting and answering your complex queries and help you resolve them. Feel free to send to ashishdhoke@projectingit.com and Ashish will get back to you.

Q.1 I want to schedule my deployment tasks on SAT / SUN. I created a new Calendar (weekend working) which I applied to task 5.1 on WBS (row 33) however the task is being rescheduled to some other day but not the weekend as I wanted. I have attached the file for your reference. Appreciate your help on this. (Fri, Nov 21, 2008 at 3:05 PM, Aman )

Ans. I checked your weekend working calendar. It is not correctly defined. You have defined SAT/SUN as working however you didn't make the other days as non -working which leaves project to schedule it on any day in the project.

Q.2 I want to create an installation task on my project such that it is scheduled uninterruptedly whenever it starts. My problem is if the predecessor tasks finishes at 12 in the afternoon than the installation task starts after but it is only scheduled until 5 pm and the remaining duration is scheduled on the next day as the task is estimated to take 10 hours. Pls guide on how to model this scenario. (Mon, Mar 9, 2009 at 1:15 PM, Amlesh )

Ans. Use 10ehr instead in the duration column. EDAY or EHour is an elapsed duration and Microsoft Project will schedule the task continuously without interrupting.

Q.3 I have entered my project Title in File, Properties. But I still can’t see the top level task that summarizes my project. Can you please help? (Apr Tue 21, 2009 at 11:15 AM, Rashmi )

Ans. Check Tools->Options->View tab and ensure you have Show Project Summary Task CHECKED. The Properties->Title is used to name the Task but displaying the task is enabled by the setting under Options.

Q.4 All my tasks are being created on “Fri 8 Jan 09” where as I entered my Project Start Date as “Mon 11 Jan 09”. I want my project tasks to be scheduled from my project start date. Please help. (Fri May 8, 2009 at 12:30 PM, Pankaj )

Ans. Please Check Tools->Options->Schedule tab and ensure you have New Tasks: Start on Project Start Date. It could be currently set to Start from Current Date.